Powering a data center:
feeders & interconnection

A data center is only as fast as its power. Here is the sequence for bringing medium-voltage power from the utility to the buildings, where projects get delayed, and why the line contractor belongs on the team early.

By Will Watson, VP of Power Line Construction · Updated October 2026

The sequence, start to finish

  1. Utility service requestThe owner or developer requests service and capacity from the serving utility. Large loads often require system studies and new utility facilities, so this step can take the longest.
  2. Design and coordinationEngineers lay out the feeder routes, duct bank, vaults and switchgear to meet the utility’s standards and the owner’s redundancy requirements.
  3. Potholing and civilExisting utilities are potholed, then crews trench, place duct bank and conduit, and set vaults, manholes and pull boxes.
  4. Feeder cable pullsMedium-voltage cable is pulled from large reels on heavy-duty reel rollers, with pull calculations and cable handling that protect the cable.
  5. Splicing and terminationsQualified cable splicers make splices, elbows and terminations to the utility’s and manufacturer’s standards.
  6. Equipment and interconnectionPad-mount transformers and switchgear are set and connected, and the utility tie-in is completed.
  7. Testing and energizationCable testing and inspections are completed, then the utility energizes service on its schedule.

Where projects get delayed

  • Utility lead times. Capacity studies, new substations and long-lead equipment can take months or longer.
  • Long-lead materials. Medium-voltage cable, switchgear and transformers often have long lead times. Order early.
  • Conflicts underground. Unknown utilities discovered during trenching stop work. Pothole first.
  • Late contractor involvement. Pull lengths, vault spacing and reel access are much easier to fix on paper than in the field.

Why bring the line contractor in early

A line contractor who reviews the design can flag pull lengths that are too long, bends that exceed cable limits, vaults without reel access and duct bank routes that will fight existing utilities. Early input keeps cable pulls safe and on schedule and avoids costly change orders.

Do not forget construction power

The site needs power long before the permanent service is energized. Temporary power poles and panels keep trailers, tools and early equipment running during construction.

FAQ

Common questions

Who coordinates with the utility?

The owner or developer requests service from the utility. GDV Utilities coordinates construction details with the utility and builds to its standards for the work we perform.

Do you self-perform the civil work?

Yes. We pothole, trench, place duct bank and conduit, and set vaults and manholes, as well as pull, splice and terminate cable.

Where do you build data center feeders?

We are licensed in California, Arizona and Nevada, including the Phoenix, Reno / Sparks, Las Vegas and Silicon Valley markets.

Is your labor union?

Yes. GDV Utilities is signatory to IBEW Local 47 and Local 1245.

Contact

Building a data center?

Send drawings or an RFP. We reply within one business day.