Temporary power pole permits:
how permitting works

Every temporary power pole needs two approvals: an electrical permit from the city or county, and a temporary service request with the utility. Here is how both work, what they need and what slows them down.

By Will Watson, VP of Power Line Construction · Updated November 2026

The two approvals every temporary pole needs

Construction power is approved in two separate places, and both have to line up before the utility energizes your pole.

  • Electrical permit: issued by the city or county building department that has jurisdiction over the job address.
  • Utility temporary service request: filed with the electric utility that serves the address. The utility's planner sets the pole location and the service point, then sets the meter after the inspection is released.

GDV Utilities handles both as part of every temporary power pole job, so you do not have to chase the building department and the utility separately.

Who issues the electrical permit

The permit comes from the building department for the job address, not the utility. Inside city limits that is the city; in unincorporated areas it is usually the county.

  • City of Los Angeles: the Los Angeles Department of Building and Safety (LADBS), including the San Fernando Valley and Pacific Palisades.
  • Other cities: the city's building and safety division, for example Corona, Riverside, Chino or Redondo Beach.
  • Unincorporated areas: the county building department, such as Riverside County or Los Angeles County.
  • Arizona and Nevada: the city development services department (for example Phoenix or Mesa) or the county for unincorporated addresses.

The permit is pulled under a licensed contractor. GDV Utilities pulls it under California license A & C-10 #1163710, Arizona license A & C-11 ROC #345427 or Nevada license C-2 #0093534.

What the permit and utility request need

  • The job address (and parcel number for vacant lots without an address yet)
  • The owner or general contractor's contact information
  • The temporary panel size, usually 100A or 200A
  • A simple site plan showing the building, the nearest utility pole or transformer and the proposed pole location
  • For the utility: the permit number, the panel size and the expected load, plus access for the utility planner to see the site

When you request a quote, a photo of the whole lot showing the nearest utility pole(s) answers most of these questions up front.

How the utility service request works

The serving utility decides where your temporary pole can go and where it will connect. Its planner reviews the request, may visit the site, and confirms the service point. After the building department releases the inspection, the utility sets the meter and energizes the pole.

Which utility you deal with depends on the address:

Inspection and release

Once the pole is set and wired, the building inspector checks the installation, typically the pole set and bracing, grounding, the meter base and panel, and the GFCI-protected receptacles. When it passes, the building department releases the inspection to the utility, and the utility schedules the meter set.

We meet the inspector on site so corrections, if any, get handled the same day.

What slows permitting down

  • No address yet on a vacant lot, or an address that does not match the parcel
  • A pole location the utility will not accept, which means a new site plan
  • Failed inspections, most often grounding or GFCI protection
  • Blocked access for the utility planner or the meter crew
  • Utility backlogs in high-demand areas, such as fire rebuild zones

Most of these are avoided by getting the pole location right the first time, which is why we ask for a photo of the lot before we quote.

FAQ

Common questions

Do I need a permit for a temporary power pole?

Yes. Temporary construction power requires an electrical permit from the city or county building department, and the utility will not energize the pole until the inspection is released.

Who pulls the permit for a temporary power pole?

GDV Utilities pulls the electrical permit under our contractor license, submits the utility temporary service request and meets the inspector. Permit fees are priced separately after the job is signed.

How long does temporary power pole permitting take?

Simple temporary power permits are often issued quickly. The utility review and meter scheduling usually take longer. We typically install within 3 to 5 business days after the permit is issued and the utility approves the service location.

Can the pole be set before the permit is issued?

No. The pole is set and wired after the permit is issued, and the utility only energizes it after the building inspection is released.