Pacific Palisades lots in the City of Los Angeles get power from LADWP. Altadena lots get it from SCE, with permits from LA County. The two utilities handle temporary power differently, and knowing which one serves your lot saves weeks.

By Will Watson, VP of Power Line Construction · Published November 2026

Which utility serves your lot

  • Pacific Palisades (City of Los Angeles): LADWP is the utility, and the Los Angeles Department of Building and Safety (LADBS) issues the electrical permit.
  • Altadena (unincorporated LA County): SCE is the utility, and LA County Public Works issues the electrical permit.
  • Malibu and other areas outside the City of LA: usually SCE. Check the address on your last electric bill if you are unsure.

Not sure which applies? Send us the lot address for a temporary power quote and we will tell you which utility and permit office handle it.

Side by side: LADWP vs. SCE

StepLADWP (Pacific Palisades)SCE (Altadena)
Electrical permitLADBS, pulled firstLA County Public Works general electrical permit
Utility requestTake the LADBS permit to an LADWP payment center and applyAn SCE service request number is required for temporary power, requested online
Overhead or undergroundMust match the lot's prior service; a pole dip can be either, and overhead is typically faster and cheaperIn SCE targeted undergrounding areas, SCE sets the service connection requirements
Typical 200A utility chargeAbout $1,200 overhead, or about $3,720 underground ($370 deposit + $3,350 balance)Set by SCE for your service
Pole placementOverhead: 10 to 100 feet from the serving pole. Underground: within 30 feet of the service lateral at the property lineSCE sets the service point
Rebuild helpPalisades Inspections and Support Center, 16925 Marquez Ave; PalisadesRebuild@LADWP.comSCE disaster recovery centers and the Altadena electric rebuild page

Utility charges are paid to the utility. LADWP lists its figures as estimates that can change with scope and amperage.

Underground service on rebuild lots

Both utilities are moving more rebuild areas underground, which changes what goes on your lot:

  • LADWP underground temporary service: call 811 (DigAlert) before digging. You install the pole and the conduit to the LADWP lateral, following LADWP standard H-168, with no more than 225 degrees of bends. LADWP inspects the conduit and pole before anything is covered, and LADBS also inspects the pole.
  • SCE targeted undergrounding: LA County advises a panel that accepts both overhead and underground service, and at least 2-inch Schedule 40 or 80 PVC conduit to the SCE service point, inspected before burial.

GDV Utilities builds both overhead and underground temporary service and coordinates the trench and conduit inspections.

Tips for rebuild owners and builders

  • Start the utility request with the building permit. Rebuild areas have long queues.
  • Ask whether your street is being undergrounded before choosing overhead temporary service.
  • Keep the pole clear of the building pad and the future driveway, so it stays put through framing.
  • Plan the permanent panel location early, so the temporary pole doesn't block it.

More on rebuild power: temporary power for fire rebuilds, Pacific Palisades, Altadena and Malibu.

Sources

FAQ

Common questions

Is Pacific Palisades served by LADWP or SCE?

Lots in the City of Los Angeles, including most of Pacific Palisades, are served by LADWP, with permits from LADBS. Malibu and areas outside the city are generally SCE.

Who serves Altadena for temporary power?

Altadena is served by SCE, and LA County Public Works issues the electrical permit. SCE requires a service request number for temporary power on rebuilds.

How much does LADWP charge for temporary power?

LADWP estimates about $1,200 for a typical 200-amp overhead temporary service and about $3,720 for underground, paid to LADWP. These are estimates and can change with scope and amperage.

Does my temporary service have to be underground?

For LADWP, temporary service must match the lot's prior service: overhead if it was overhead, underground if it was underground. In SCE targeted undergrounding areas, SCE sets the requirements.

Contact

Get a firm quote

Send your site details and photos. We reply within one business day.

Free: Fire Rebuild Power Guide
LADWP vs. SCE steps for Palisades and Altadena lots, plus underground service planning.
Get the guide