The short answer
Take the busbar rating on your panel label, multiply by 1.2, and subtract the main breaker size. What is left is the largest solar breaker the panel can take when that breaker sits at the opposite end of the busbar from the main. Get a panel upgrade quote with a load review.
Busbar rating x 1.2 − main breaker = largest solar breaker
A panel with a 200 amp busbar and a 200 amp main: 200 x 1.2 = 240, minus 200 = 40 amps.
Quick table by panel size
| Busbar | Main breaker | Largest solar breaker | Approx. max inverter output at 240V |
|---|---|---|---|
| 100A | 100A | 20A | 3.8 kW |
| 125A | 100A | 50A | 9.6 kW |
| 200A | 200A | 40A | 7.7 kW |
| 200A | 175A | 65A | 12.5 kW |
| 200A | 150A | 90A | 17.3 kW |
| 225A | 200A | 70A | 13.4 kW |
The solar breaker must also be at least 125% of the inverter's continuous output, which is why the last column is lower than the breaker size. Real systems use standard breaker sizes, so treat this as a first check, not a design.
The conditions that come with it
- Opposite end. The solar breaker must be at the opposite end of the busbar from the main breaker.
- Dedicated breaker. The inverter connects through its own breaker or fused disconnect.
- Batteries count. A battery inverter that backfeeds the same panel adds to the total, so solar plus storage can run out of room faster.
- EV chargers are different. A charger is a load, not a source. It affects your load calculation and service size, not the 120% rule. See panel upgrades for solar and EV.
If your panel fails the rule
| Option | What it means | When it works |
|---|---|---|
| Derate the main | Replace the main breaker with a smaller one, which frees up room on the busbar | When a load calculation shows the house runs fine on the smaller main |
| Supply-side connection | Connect the solar ahead of the main breaker instead of through a backfed breaker | When the meter-main equipment and the utility allow it |
| New panel or busbar | Install a panel with a higher busbar rating, such as a 225A bus with a 200A main | When you also need more breaker space or plan EV charging |
| Service upgrade | Increase the service size with the utility | When the load calculation says the house needs more capacity |
A main panel upgrade needs a utility disconnect and reconnect. SCE's published targets for the SCE-controlled part of a main panel upgrade are an average of 30 business days and a maximum of 45.
How to check your own panel
- Open the panel door and find the label, usually inside the door or on the side of the box.
- Write down the busbar rating. It may read "bus rating" or "max amps".
- Read the number on the main breaker handle.
- Run the formula above, or download our free panel upgrade sizing sheet and send us a photo of the label.