The short answer
Most temporary power corrections fall into five groups: GFCI protection, grounding, how the pole is set, the panel, and labeling. Exact rules vary by city and county, so the numbers below come from two published California examples: the Los Angeles Department of Building and Safety (LADBS) bulletin on temporary poles and the City of Roseville's temporary pole handout. Check your own jurisdiction's handout too. Get a temporary power pole quote that includes the inspection.
The items inspectors flag most
| Item | What the inspector looks for |
|---|---|
| GFCI protection | 120-volt, single-phase 15, 20 and 30 amp receptacles must be GFCI protected (LADBS). Roseville requires GFCI on all 120-volt outlets. |
| Weather-resistant receptacles | 15 and 20 amp, 125/250 volt receptacles marked WR, with a listed extra-duty cover hood (LADBS). |
| Ground rod depth | Driven at least 8 feet (LADBS and Roseville). LADBS calls for undisturbed soil. |
| Number of electrodes | Two electrodes at least 6 feet apart, unless a single electrode tests at 25 ohms or less (LADBS). |
| Grounding conductor | No. 8 AWG copper minimum, in metallic raceway or cable armor (LADBS). Roseville wants conduit or flex run continuously from the panel to the rod. |
| Pole size and setting | LADBS: wood pole at least 6 x 6 inches (or 5 inches round), at least 20 feet long, embedded at least 4 feet. Roseville overhead service: 4 x 6 post minimum, 4 feet deep, drip loop at least 10 feet above grade. |
| Underground service post | Roseville: 4 x 4 post minimum, 18 inches deep, meter 48 to 75 inches above grade. |
| Panel | Mounted firmly, unused openings closed, unused breakers removed (unless GFCI type), all circuits identified (Roseville). |
| Conduit and meter section | Conduit secured to the pole with a bushing, cord clamps installed, sealing screw on the meter section (Roseville). LADBS: vertical raceway at least 3/4 inch, supported at least every 3 feet. |
| Nothing hung on the pole | No lights, signs, ropes or similar items attached to the pole (LADBS). |
| Address | Address posted where the inspector can see it (Roseville). |
Pre-inspection checklist
- Press the test button on every GFCI and make sure it trips and resets.
- Confirm every receptacle is WR rated and has an in-use cover that closes with a cord plugged in.
- Confirm the ground rod is fully driven and the grounding conductor is protected and tight at both ends.
- Look at the panel: no open knockouts, no missing breaker blanks, every circuit labeled.
- Confirm conduit straps, bushings and the meter sealing screw are in place.
- Take anything hanging off the pole down.
- Post the address and keep the permit card on site.
- Make sure the inspector can reach the pole: gate unlocked, no dogs, no material stacked in front of the panel.
- Confirm the pole is where the utility approved it. An inspection pass does not help if the utility will not serve that location.
What a failed inspection costs you
A failed inspection means a correction notice, a fix and a new inspection request. The utility only sets the meter after the inspection is released, so every reinspection pushes power back. See the SCE temporary power timeline for how the steps stack up, and the permit guide for the permit side.
How GDV Utilities handles inspection
GDV Utilities sets and wires temporary poles to the local handout and the serving utility's requirements, then coordinates the inspection. If the inspector writes a correction, our crew fixes it so the release can go to the utility. Removal is included: we track the job and schedule removal once permanent power is energized.