100A vs. 200A temporary power:
which does your job need?

A 100-amp temporary panel covers most single-home and ADU builds running hand tools, compressors and lighting. Choose 200 amps when several trades work at once or the site runs welders, electric heat or a site office. Here is how to decide.

By Will Watson, VP of Power Line Construction · Published November 2026

The quick answer

  • 100 amps: one home, an ADU or a remodel, with hand tools, saws, compressors, chargers and work lights.
  • 200 amps: larger homes, several trades working at the same time, welders, electric heaters or drying equipment, or a site office with air conditioning.
  • 400 amps: multi-unit and commercial sites with heavy equipment.

Get a temporary power quote for 100A or 200A and we will help you size it.

Which size fits which job

PanelTypical jobTypical loads
100ASingle-family home, ADU, remodelCircular and miter saws, drills, a compressor, battery chargers, work lights
200ALarger homes, fast schedules with several trades, fire rebuildsEverything above, plus welders, electric heaters, drying fans, a site office or trailer
400AMulti-unit and commercial constructionMultiple trailers, heavy welding, large heaters, hoists

Signs you need the bigger panel

  • Two or more trades will run heavy tools at the same time.
  • The site will use electric heat, curing blankets or dehumidifiers in winter.
  • Someone will weld on site.
  • There will be a job trailer or office with heating or air conditioning.
  • The schedule is tight, and tripped breakers would cost a crew hours.

What happens if you choose too small

An undersized panel trips breakers and slows crews down. Upsizing mid-project usually means a new permit, a new inspection and sometimes a new utility request, so it is cheaper to choose right the first time. If you are between sizes, choose 200 amps.

The utility can also limit what it will serve: LADWP's standard temporary service process covers single-phase service up to 400 amps, with 200 amps as its typical example. See the permit guide and rent or buy.

Sources

FAQ

Common questions

Is 100 amps enough for temporary power on a house?

For most single-family homes and ADUs running hand tools, saws, compressors and lights, 100 amps is enough. Choose 200 amps if several trades, welders or electric heaters will run at once.

When do I need a 200-amp temporary power pole?

When several trades work at the same time, someone welds on site, the site uses electric heat or drying equipment, or there is a job trailer with heating or air conditioning.

Can I upgrade from 100A to 200A later?

Yes, but it usually means a new permit and inspection, and sometimes a new utility request, so it is cheaper to size right at the start.

Do you offer 400-amp temporary power?

Yes. GDV Utilities offers 100A, 200A and 400A temporary power for residential, multi-unit and commercial projects.

Contact

Get a firm quote

Send your site details and photos. We reply within one business day.

Free: Temp Power Checklist
Permit to energize in six steps, plus who serves your lot and what causes delays.
Get the checklist