Rule 15 vs. Rule 16
line and service extensions

New buildings, subdivisions and commercial sites in California get utility power under two tariff rules: Rule 15 for distribution line extensions and Rule 16 for service extensions. They decide what the utility pays for, what you pay for, and what work you can hire your own contractor to build.

By Will Watson, VP of Power Line Construction · Published November 2026

The short answer

Rule 15 covers distribution extensions: the lines and mains along streets that serve more than one customer. Rule 16 covers service extensions: the wiring from the distribution line to one meter. A subdivision usually needs both: a Rule 15 extension to bring the line in, and a Rule 16 service to each lot. Ask GDV Utilities to price your applicant work.

Side by side

Rule 15: distribution extensionRule 16: service extension
What it coversLines and mains along streets that serve multiple customersWiring from the distribution line to one meter
AllowancesRevenue-based, from permanent loadsRevenue-based, from permanent loads
PaymentsRefundable and non-refundable charges. The refundable advance and some substructure costs can be refunded over 10 years, or you can take a discount option insteadNon-refundable only. SCE: "All service extension payments are non-refundable and non-discountable."
SCE max energization target*245 business days230 business days

*For the SCE-controlled steps only. SCE's average target for both is 125 business days, and 210 business days maximum for combined Rule 15/16 projects.

How allowances work

  • The utility gives an allowance based on the permanent, bona fide load the extension will serve.
  • Residential projects get a standard allowance per unit, with six months to connect the load.
  • Non-residential projects get a site-specific estimate, with one year to connect.
  • No allowance is given for insignificant loads such as gate openers.
  • If the allowance covers the utility's estimated installed cost, the extension is built without charge. If not, you pay the difference.

Applicant installation: work you can hire out

SCE's customer guide lets applicants use a qualified independent installer instead of the utility for part of the job. For underground electric work, the applicant can:

  • Do the trenching, excavation, backfill and compaction, or pay the utility to do it.
  • Install the distribution conduit and substructures and deed them to the utility, or pay the utility to install them.
  • Install protective structures such as fences, retaining walls and barricades, and deed them to the utility.

The utility furnishes, installs and maintains the poles, conductors, cables, switches and transformers. For overhead extensions, the applicant's part is limited to providing a clear route and paying for permits.

Keeping the project moving

  • Complete application. SCE's energization clock starts when it deems the application complete. Its target for approving or rejecting an application averages 10 business days, with a maximum of 45.
  • Site readiness is on you. On non-Rule 29 projects, the customer schedules and completes all onsite civil construction before SCE builds.
  • Permits and easements. These are customer dependencies that SCE does not control.
  • Temporary power. Construction can start on a temporary power pole while the permanent service is in process.

Rule 29 is a separate rule for EV charging infrastructure, where SCE handles the onsite civil work. See line extensions and new service for what GDV Utilities builds.

Sources

FAQ

Common questions

What is the difference between Rule 15 and Rule 16?

Rule 15 covers distribution line extensions, the lines and mains along streets that serve multiple customers. Rule 16 covers service extensions, the wiring from the distribution line to one customer's meter.

Are Rule 16 service extension payments refundable?

No. SCE's customer guide says all service extension payments are non-refundable and non-discountable.

Can I hire my own contractor for a line extension?

Yes, for part of the work. Under the applicant installation option, a qualified independent installer can do the trenching, conduit and substructures and protective structures, which are then deeded to the utility. The utility installs the cable and electrical equipment.

How long does a Rule 15 or Rule 16 project take with SCE?

SCE's published average target for the SCE-controlled steps is 125 business days, with maximums of 245 business days for Rule 15 and 230 for Rule 16. Permits, easements and onsite civil work are on top of that.

Contact

Get a firm quote

Send your site details and photos. We reply within one business day.

Free: Temp Power Checklist
Permit to energize in six steps, plus who serves your lot and what causes delays.
Get the checklist