GDV Utilities
Guide

How long does SCE take
to energize a temp pole?

SCE does not publish a fixed timeline for temporary construction power. The meter goes on after three things line up: the electrical permit, SCE's approval of the service point, and a released inspection. Here are the steps, who controls each one and how to keep them short.

By Will Watson, VP of Power Line Construction · Published November 2026

The short answer

Your temporary pole is energized when SCE sets the meter, and SCE only does that after the building department releases the inspection. So the timeline is the sum of three tracks: the city or county permit, SCE's review of your service request, and the inspection. Get a temporary power pole quote with the permit and SCE request included.

  • SCE planner contact: SCE says a local service planner contacts you within 5 business days of the service request.
  • Pole set: GDV Utilities sets the pole 3 to 5 business days after the permit is issued and SCE approves the location.
  • Meter set: SCE schedules it after the inspection is released. SCE publishes no standard wait for this step on temporary service.

Step by step: who controls each wait

StepWhoWhat to expect
1. Electrical permitCity or county building departmentSimple temporary power permits are often issued quickly; it depends on the department.
2. SCE service requestYou or your contractor, to SCESubmitted online or by phone (1-800-655-4555, option 3). A planner contacts you within 5 business days.
3. Planner reviewSCE service plannerMay ask for a Temporary Power application and a site plan, and may visit the site to set the service point.
4. Pole set and wiringGDV Utilities3 to 5 business days after the permit is issued and SCE approves the location.
5. InspectionBuilding inspectorScheduled with the building department after the pole is set.
6. Release and meter setBuilding department, then SCEThe department releases the inspection to SCE, and SCE schedules the meter set.

Steps 1 and 2 can run at the same time. Most of the calendar time is spent waiting on the permit and SCE, not on the pole itself.

What makes SCE take longer

  • Missing information. No address on a vacant lot, a wrong parcel number or no site plan sends the request back.
  • A pole location SCE won't accept. The planner sets the service point. If the pole is in the wrong place, you start over with a new plan.
  • A failed inspection. Grounding and GFCI protection are the usual failures, and SCE cannot set the meter until the inspection is released.
  • Blocked access. The planner and the meter crew need to reach the pole.
  • Utility work needed first. If SCE has to extend a line or add a transformer, the job becomes a line or service extension under SCE Rules 15 and 16. SCE's own target for those is an average of 125 business days, so plan far ahead.
  • High-demand areas. Fire rebuild zones such as Altadena and Malibu have more requests in the queue. See temporary power for fire rebuilds.

How to get power sooner

  1. Order temp power when you pull the building permit, not when the slab is poured.
  2. Send a photo of the lot that shows the nearest utility pole, so the pole location is right the first time.
  3. Have the address or parcel number ready, plus the owner's or general contractor's contact information.
  4. Keep the pole area clear and reachable for the planner, the inspector and the meter crew.
  5. Use a contractor who meets the inspector, so any correction is fixed the same day.

GDV Utilities handles the permit, the SCE request and the inspection on every temporary power pole job. See the permit guide for how the two approvals fit together.

Sources

FAQ

Common questions

How long does SCE take to set a temporary power meter?

SCE does not publish a fixed timeline for temporary service. The meter is set after the building department releases the inspection, and the total wait depends on the permit, SCE's planner review and the inspection.

How fast does SCE respond to a temporary power request?

SCE says a local service planner contacts you within 5 business days of the service request.

Can the pole be set before SCE approves the location?

We set the pole after the permit is issued and SCE approves the location, typically within 3 to 5 business days. Setting it before approval risks having to move it.

Does GDV Utilities handle the SCE request?

Yes. Every GDV Utilities temporary power pole quote covers the electrical permit, the SCE service request, the pole and panel, the inspection and removal.

Contact

Get a firm quote

Send your site details and photos. We reply within one business day.

Free: Temp Power Checklist
Permit to energize in six steps, plus who serves your lot and what causes delays.
Get the checklist